Narrative:

The problem of descending 400 ft below an assigned altitude was caused by the fact the PF was briefing the approach into O'hare while also flying the aircraft. This could have been avoided by xferring the controls to the PNF. As we descended through 7000 ft we noticed the continued descent and corrective action was taken to climb back to 7000 ft.

Google
 

Original NASA ASRS Text

Title: EMB145 ALTDEV ORD.

Narrative: THE PROB OF DSNDING 400 FT BELOW AN ASSIGNED ALT WAS CAUSED BY THE FACT THE PF WAS BRIEFING THE APCH INTO O'HARE WHILE ALSO FLYING THE ACFT. THIS COULD HAVE BEEN AVOIDED BY XFERRING THE CTLS TO THE PNF. AS WE DSNDED THROUGH 7000 FT WE NOTICED THE CONTINUED DSCNT AND CORRECTIVE ACTION WAS TAKEN TO CLB BACK TO 7000 FT.

Data retrieved from NASA's ASRS site as of July 2007 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.