Narrative:

The aircraft had a history of fuel system failures associated with center tank pump 2. These appeared to be sequencing failures; and thus maintenance ran and passed a sequencing test. On taxi out; a subsequent ECAM for center tank pump 1 appeared. As the resulting ECAM was followed; the ECAM disappeared; and all systems were functioning normally. This continued until after takeoff and into climbout; when the center tank pumps should begin to sequence on. The pumps failed to sequence on; with center tank pump 1 showing low pressure and center tank pump 2 showing itself stuck in the standby mode. The associated ECAM's were completed; and attempts to restore pump operation through manual mode were unsuccessful. At that point; we checked the circuit breaker panel and discovered that center tank pump 1 circuit breaker was out. We then remembered the mechanic complaining about a circuit breaker that was difficult to operate in conjunction with his test and thought that may be the reason pump 1 had low pressure. Nonetheless; we reviewed our options and considered landing enroute as useable fuel was insufficient to continue all the way to our destination. Dispatch; maintenance control and ATC were all brought into the loop and after all procedures were completed the event concluded with an uneventful landing and a replacement aircraft was obtained to complete the trip.

Google
 

Original NASA ASRS Text

Title: When chronic fuel pump problems resurfaced enroute the flight crew of an A319 was forced to land short of their destination due to insufficient accessible fuel. A substitute aircraft was utilized to complete the scheduled flight.

Narrative: The aircraft had a history of fuel system failures associated with CTR Tank Pump 2. These appeared to be sequencing failures; and thus Maintenance ran and passed a sequencing test. On taxi out; a subsequent ECAM for CTR Tank Pump 1 appeared. As the resulting ECAM was followed; the ECAM disappeared; and all systems were functioning normally. This continued until after Takeoff and into climbout; when the CTR tank pumps should begin to sequence on. The pumps failed to sequence on; with CTR Tank Pump 1 showing low pressure and CTR Tank pump 2 showing itself stuck in the standby mode. The associated ECAM's were completed; and attempts to restore pump operation through manual mode were unsuccessful. At that point; we checked the CB panel and discovered that CTR Tank Pump 1 CB was out. We then remembered the mechanic complaining about a CB that was difficult to operate in conjunction with his test and thought that may be the reason Pump 1 had low pressure. Nonetheless; we reviewed our options and considered landing enroute as useable fuel was insufficient to continue all the way to our destination. Dispatch; Maintenance Control and ATC were all brought into the loop and after all procedures were completed the event concluded with an uneventful landing and a replacement aircraft was obtained to complete the trip.

Data retrieved from NASA's ASRS site as of July 2013 and automatically converted to unabbreviated mixed upper/lowercase text. This report is for informational purposes with no guarantee of accuracy. See NASA's ASRS site for official report.